Q: When will McLane Road be paved?

A: While paving McLane was originally scheduled to begin Oct. 1, the contractor is ahead of schedule. Paving actually began Sept. 25, and is now complete," said La Ron Garrett, public works engineer for the Town of Payson. "The striping is scheduled to begin next week."